Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • This control is done automatically by taking R = 1 by the program.

  • Since it is necessary to make an analysis to see the results of this control, it is necessary to do an analysis after selecting R and D and pay attention to the warnings in the control of shearwall overturning moment section in the earthquake regulation code general report.

...

  • In the report visuals given above for the X direction, it is seen that (4/5) R is taken instead of R for the X direction, since item (a) does not provide. The same is true for the Y direction.

  • As a result of the controls in the building, it is necessary to use (4/5) R in both directions, so the relevant boxes next to the R coefficients in the analysis settings should be marked and re-analyzed. Post marking program (4/5) uses R in accounts and reports that the transaction is correct by showing that it is used in tipping overturning reports.

...