Construction Cost Estimating Reports

For the cost calculation, the currency unit, the unit cost of the material and the amount of the material used in the material are defined. After this stage, the material in question is assigned to the object and the report is prepared by selecting the cost account in the quantity of building components.

Location of the Construction Cost Estimating

You can access it from the Select Report dialog that opens when the components report command is clicked.

Usage Steps

  • Components Report icon in the ribbon menu .

  • The Select Report dialog will open.

  • From dialogue, select the Construction Cost Estimating line.

  • Click the OK button. The report will be generated.

Construction cost estimating report (unit costs belong to previous years)


Next Topic

Creating Quantity Report According to DIN277 and II BV Standard