Steel tie deflection limit exceeded.

This message is created by specifying the element name and floor on which it is located at the beginning of the report.

For example,

T01 BASE STORY Beam deflection limit exceeded.

Deflection check for steel elements is carried out under gravity loads such as dead loads, live loads, and snow loads, depending on user control by CYTHYE 2016 (GKT & YDKT), AISC 360-16 (ASD & LRFD) or EN 1993-1-1 codes.

image-20240124-113109.png

Possible Solutions:

  • Steel element cross-section can be enlarged.

  • It can be determined by checking the steel element deflection limit according to the given steel design codes.

  • Steel purlin spacing can be reduced.


Next Topic