in Article 7.6.7.2 of TBDY , Vertical reinforcement in horizontal construction joints to be made at the connection level to the foundation and on the upper floors will be controlled by the shear friction method defined in TS 500, taking into account the shear force transferred in that section.

This error message is given because the value does not meet the conditions given in this article.

Possible Solutions

  • The cross section of the curtain / column can be increased.

  • The longitudinal stiffness on the shear surface of the shear/column can be increased.

  • Concrete class can be increased.

  • The design can be updated to reduce the shear force on the element.

  • Concrete casting methods can be improved to suit the application and project.

 

Next Topic

Related content

TBDY 7.11.5 in connection of elements with shearwall. conditions were not met.
TBDY 7.11.5 in connection of elements with shearwall. conditions were not met.
More like this
Shearwall Design Shear Strength Report
Shearwall Design Shear Strength Report
More like this
Wall Shear Design Report (7.6.6.3)
Wall Shear Design Report (7.6.6.3)
More like this
Parallel and Perpendicular Reinforcement as Collector Elements (7.11.5)
Parallel and Perpendicular Reinforcement as Collector Elements (7.11.5)
More like this
Polygonal Cross-Section Shearwall Design Shear Forces
Polygonal Cross-Section Shearwall Design Shear Forces
More like this