Strip Footing Maximum Pursmail Exceeded.

This message is created at the beginning of the report by giving the name of the element and its solid.

For example, TK1011 Basement Floor Maximum pursuit has been exceeded

In the element given its name and solid, it means that the required reinforcement ratio calculated from the design effects exceeds the upper limit reinforcement ratio given in the regulation.

Possible solutions:

  • The analysis should be repeated by enlarging the sections of the relevant element.