Slab deflection limit exceeded
The deflection value of the slab means that it exceeds the upper deflection limit.
This message is created at the beginning of the report by giving the element name and solid.
For example, D01 1st Floor Slab deflection limit was exceeded.
The deflection control of the floors is made according to the principles given in TS 500 13.2 .
Solution:
Increase the dimensions of the floor given the name and floor until the deflection condition is met.
Repeat the analysis after the size increase.